Contract
No: HK/2009/05 Wanchai Development Phase II and Sampling, Field Measurement and
Testing Work (Stage 1) Environmental
Permit no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A,
FEP-05/364/2009/A,
FEp-06/364/2009/a and FEP-07/364/2009/A Monthly
Environmental Monitoring & Audit Report
- March 2011 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics
Limited 11/F Centre
Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
6 April
2011 |
2.2 Scope
of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
3. status of regulatory compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
5.2 Real Time Noise Monitoring Results
6.2 Real Time Noise Monitoring
6.4 Review
of the Reasons for and the Implications of Non-compliance
6.5 Summary
of action taken in the event of and follow-up on non-compliance
7. Cumulative Construction Impact due to the
Concurrent Projects
9. Complaints,
Notification of Summons and Prosecution
lIST
OF TABLES
Table 2.1 Schedule 2
Designated Projects under this Project
Table 2.2 Details of
Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/17
Table 3.3 Summary of
submission status under FEP-03/364/2009
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. 04/HY/2006
Table 3.5 Summary of
submission status under FEP-04/364/2009/A
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Table 3.7 Summary of
submission status under FEP-02/364/2009
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Table 3.9 Summary of
submission status under FEP-01/364/2009
Table 3.10 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/18
Table 3.11 Summary of
submission status under FEP-05/364/2009/A
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Table 3.13 Summary of
submission status under FEP-06/364/2009/A
Table 3.14 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/19
Table 3.15 Summary of
submission status under FEP-07/364/2009/A
Table 4.1 Noise
Monitoring Stations
Table 4.2 Real Time
Noise Monitoring Stations
Table 4.3 Air
Monitoring Stations
Table 5.1 Noise
Monitoring Stations for Contract no.
HY/2009/17
Table 5.2 Noise
Monitoring Stations for Contract nos. 04/HY/2006 and HY/2009/18
Table 5.3 Noise
Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02
Table 5.4 Noise
Monitoring Stations for Contract no. HY/2009/15
Table 5.5 Noise
Monitoring Stations for Contract no. HY/2009/19
Table 5.6 Real Time
Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.7 Real Time
Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Air
Monitoring Station for Contract no. HY/2009/17
Table 5.9 Air
Monitoring Stations for Contract no. 04/HY/2006 and HY/2009/18
Table 5.10 Air
Monitoring Station for Contract no. HK/2009/01
Table 5.11 Air
Monitoring Station for Contract no. HK/2009/02
Table 5.12 Air
Monitoring Station for Contract no. HY/2009/15
Table 5.13 Air
Monitoring Stations for Contract no. HY/2009/19
Table 5.12 Details of
Waste Disposal for Contract no. HY/2009/17
Table 5.13 Details of
Waste Disposal for Contract no. 04/HY/2006
Table 5.14 Details of
Waste Disposal for Contract no. HK/2009/01
Table 5.15 Details of
Waste Disposal for Contract no. HK/2009/02
Table 5.16 Details of
Waste Disposal for Contract no. HY/2009/18
Table 5.17 Details of
Waste Disposal for Contract no. HY/2009/15
Table 5.18 Details of
Waste Disposal for Contract no. HY/2009/19
Table 8.1 Summary of
Environmental Inspections for Contract no. HY/2009/17
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental
Monitoring Stations
lIST OF APPENDIces
Appendix
3.1 Environmental
Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix
5.1 Monitoring
Schedule for Reporting Month and Coming month
Appendix
5.2 Noise Monitoring
Results and Graphical Presentations
Appendix
5.3 Air Quality Monitoring Results and Graphical Presentations
Appendix 5.4 Real-time Noise Monitoring Results and
Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling
works under FEP-03/364/2009
·
Piling Works.
Contract no. HY/2009/18 - Central - Wan Chai Bypass
(CWB) - Central Interchange under
FEP-05/364/2009/A
·
No major construction activity was undertaken in
reporting month. Only preparation works was commenced in the reporting month.
·
Condition survey / Instrumentation Manholes and
Intake Culvert Survey
·
Cable detection and excavation of trial pit
·
Hoarding and project signboard erection
·
CLC construction works
·
Tree transplanting
·
Provision of site welfare facilities
·
Trial installation of coupler in CR3
·
TTA for Man Po / Man Kwong diversion
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street
and Man Kwong Street under FEP-04/364/2009/A
·
Major construction works were completed and Engineer’s
confirmation for completion of work is under processing in this reporting month.
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at
·
No major construction activity was undertaken in
reporting month.
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
·
No major construction activity was undertaken in
reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
·
No major construction activity was undertaken in
reporting month.
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
·
Carry out Independent Hydrographic Survey
·
Install fencing at the Pier F3-15
·
Steel fabrication of temporary platform for
pre-drilling
Noise Monitoring
Air Monitoring
Complaints, Notifications of
Summons and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
·
Piling Works
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
·
No major construction activity was undertaken in
next reporting month. Only preparation work was commenced.
·
Condition survey / Instrumentation Manholes and
Intake Culvert Survey
·
Cable detection and excavation of trial pit
·
Hoarding and project signboard erection
·
Tree transplanting
·
Provision of site welfare facilities
·
Trial installation of coupler in CR3
·
Temporary drainage diversion works
·
TTA for Man Po / Man Kwong diversion
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street
and Man Kwong Street under FEP-04/364/2009/A
· Major construction
works were completed and Engineer’s confirmation for completion of work is
under processing.
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at
·
No major
construction activities are anticipated in coming reporting month.
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
·
No major
construction activities are anticipated in coming reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
·
No major
construction activity was undertaken in coming reporting month.
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
·
Steel
fabrication of temporary platform for pre-drilling
·
Installation
of working platform to enable pre-drilling works
·
Marine
pre-drilling
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A to
implement the Environmental Monitoring and Audit (EM&A) programme as stipulated
in the EM&A Manual of the approved Environmental Impact Assessment (EIA)
Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register
No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of
EM&A Manual and “Environmental Monitoring and Audit
Requirements” under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/A,
Further Environmental Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009,
FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A
during the period 28th February to 27th March 2011. The cut-off date of reporting is at 27th of
each reporting month.
Section 1 Introduction – details the scope and structure of the
report.
Section 2 Project Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Status of
Regulatory Compliance – summarizes the status of valid Environmental Permits /
Licenses during the reporting period.
Section 4 Monitoring Requirements – summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section 5 Monitoring Results – summarizes the monitoring results
obtained in the reporting period.
Section 6 Compliance Audit – summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Site Inspection
– summarizes
the findings of weekly site inspections undertaken within the reporting period,
with a review of any relevant follow-up actions within the reporting period.
Section 9 Complaints,
Notification of summons and Prosecution – summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 10 Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai
Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
Design and Construction of Central – Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope of
the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
·
A dual three-lane trunk road, approximately 4.5 km
in length, and tunnel approximately 3.7 km in length defined from the
connection with the existing Rumsey Street Flyover in Central, through to a
connection with the existing Island Eastern Corridor to the east of the
Causeway Bay Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey Street
Flyover to provide road connections to the Central area;
·
Tunnel control buildings and ventilation buildings;
·
Slip roads to connect the CWB to the local road
system in the Wan Chai North and
·
Associated road lighting, road signing, traffic
control and surveillance system; and
·
Other associated works.
2.2.3.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
In
the reporting month, advance piling work
at FEHD Whitfield Depot under Contract no. HY/2009/17 was commenced on 5
October 2010 and pending to construct one pile cap. In addition, Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
under HY2009/19 was commenced on 24 March
2011 .The details of individual contracts are summarized in Table2.2.
Table
2.2 Details of Individual Contracts
under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
Anticipated to be commenced in April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 |
HK/2009/01 |
Wan Chai Development Phase II - Central - Wan Chai Bypass at |
DP1, DP2 |
Pending |
HK/2009/02 |
Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai
East(CWB Tunnel) (CWB Tunnel) |
DP1 |
Pending |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel ( |
DP1 |
Pending |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Lam
Woo & CO., LTD. |
Contractor under Contract no. HY/2009/17 |
Project Manager |
Mr. K. S. Law |
9090 1378 |
2566 7522 |
Construction Manager / Sub Agent |
Mr. Joe Tsang |
9725-5874 |
|||
Site
Agent |
Mr. Daniel Chan |
9372 0495 |
|||
Environmental Officer |
Mr. Andy Mak |
6461 3065 |
|||
Chiu Hing Construction & Transportation Co. Ltd. |
Contractor under Contract no. 04/HY/2006 |
Contract Manager |
Mr. Frederick Tsui |
2967 6363 |
2967 6366 |
Senior Site Agent |
Mr. Alvin Ma |
2967 6363 |
2967 6366 |
||
Environmental Consultant |
Mr. Jimmy Cheng |
2965 0898 |
2556 9172 |
||
Chun Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
2634 1626 |
Operation
Manager |
Mr. Ho Wing Tai |
9306 1356 |
|||
Construction
Manager |
Mr. David Wong |
9653 8635 |
|||
Construction
Manager |
Mr. Wilson Lau |
5183 1270 |
|||
Construction
Manager |
Mr. Alex Tsang |
9194 9383 |
|||
Environmental
Officer (Compliance Manager) |
Mr.Ho Wing Tai |
9306 1356 |
|||
Environmental Engineer |
Mr. Ken Yang |
9262 6791 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Site Agent |
Mr. Eric Lam |
3658-3048 |
|||
Deputy Site Agent |
Mr. Anthony Wu |
3658-3004 |
|||
Environmental Officer (Compliance Manager) |
Mr. Barry Leung |
3658 3031 |
|||
Environmental Engineer |
Ms. Flora Ng |
3658-3064 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Construction Manager |
Mr. William Luk |
9610 1101 |
|||
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental Officer |
Mr. Simon Wong |
9281 4346 |
|||
Leighton Contractors ( |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Brian Gillon |
2214 7700 |
2140 6799 |
Deputy Site Agent |
Mr. Desmond Sze |
2214 7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214 7721 |
|
||
Environmental Supervisor |
Mr. Dennis Yu |
2214 7738 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Manager |
Mr. M Y Wong |
2823 7879 |
2566 2192 |
Site Agent |
Mr. Leung Kwok Yiu |
9026 8808 |
|||
Head of construction |
Mr. Simon Tang |
9022 6060 |
|||
Construction Manager |
Mr. C K Kwok |
9779 2162 |
|||
Assistant Construction Manager (East) |
Mr. Gene Cheung |
6105 4880 |
|||
Assistant Construction Manager (West) |
Mr. Tony Chiu |
9090 0606 |
|||
Section Agent (East) |
Mr. Jason Chan |
9254 1635 |
|||
Section Agent (West) |
Mr. Tang Ka Tung |
9473 4771 |
|||
Environmental Manager |
Ms. Anna Yu |
9473 1945 |
|||
Environmental Officer |
Mr Kelven Yip |
9669 5447 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In the reporting month, the principal work
activities of individual contracts are included as follows:
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
·
Major construction work was completed in this reporting
month and Engineer’s confirmation for completion of work is under processing.
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
·
Piling Works
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB)
- Central Interchange under FEP-05/364/2009/A
·
No major construction activity was undertaken in
reporting month. Only preparation works was commenced in the reporting month.
·
Condition survey / Instrumentation Manholes and
Intake Culvert Survey
·
Cable detection and excavation of trial pit
·
Hoarding and project signboard erection
·
CLC construction works
·
Tree transplanting
·
Provision of site welfare facilities
·
Trial installation of coupler in CR3
·
TTA for Man Po / Man Kwong diversion
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
·
No major construction activity was undertaken in
reporting month.
Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
·
No major construction activity was undertaken in
reporting month.
Contract no.
HY/2009/15 - Central-Wanchai Bypass – Tunnel (
·
No major construction activity was undertaken in
reporting month.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under
FEP-07/364/2009/A
·
Carry out Independent Hydrographic Survey
·
Install fencing at the Pier F3-15
·
Steel fabrication of temporary platform for
pre-drilling
2.4.4.
In
coming reporting month, the principal work activities of individual contracts
are anticipated as follows:
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street
and Man Kwong Street under FEP-04/364/2009/A
·
Major construction work was completed in this
reporting month and waiting Engineer’s formal confirmation for completion of
work.
Contract no. HY/2009/17 - Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
·
Piling
Works.
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
·
No major construction activity was undertaken in
next reporting month. Only preparation works will be commenced.
·
Condition survey / Instrumentation Manholes and
Intake Culvert Survey
·
Cable detection and excavation of trial pit
·
Hoarding and project signboard erection
·
Tree transplanting
·
Provision of site welfare facilities
·
Trial installation of coupler in CR3
·
Temporary drainage diversion works
·
TTA for Man Po / Man Kwong diversion
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at
·
No major
construction activity is anticipated in coming reporting month.
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
·
No major
construction activity is anticipated in coming reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
·
No major
construction activity was undertaken in coming reporting month.
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
·
Steel
fabrication of temporary platform for pre-drilling
·
Installation
of working platform to enable pre-drilling works
·
Marine
pre-drilling
3.1.1. A summary of the current status on licences
and/or permits on environmental protection pertinent to the Project is shown in
Table
3.1.
Permits and/or
Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Valid |
|
Further Environmental Permit |
14 Oct 2010 |
Valid |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
3.1.2. Due to the multi-contract nature of the Project,
the status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no.
HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works under FEP-03/364/2009
3.1.3. Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under
FEP-03/364/2009 for
contract no. HY/2009/17 showed in Table 3.2 and Table 3.3.
Table
3.2 Cumulative Summary of Valid
Licences and Permits under Contract no.
HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul 2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010 – 31 Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13 May 2010 |
N/A |
Valid |
Billing Account
under Waste Disposal Ordinance |
7010400 |
16 Mar 2010 |
N/A |
Valid |
Table 3.3 Summary of submission status under FEP-03/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
18 September 2010 |
Conditions 2.7 and
2.8 |
Submission of works schedule and location plan |
1 September 2010 |
Condition 2.9 |
Noise Management Plan |
1 September 2010 |
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus
near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
3.1.4. Summary of the current status on licences and/or
permits on environmental protection pertinent and submission under
FEP-04/364/2009/A for
contract no. 04/HY/2006 are shown in Table 3.4 and Table 3.5.
Table 3.4 Cumulative Summary of Valid Licences and
Permits under Contract no. 04/HY/2006
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
N/A |
Valid |
Notification of Works Under APCO |
322225 |
7 Oct 2010 |
N/A |
Valid |
Billing Account
under Waste Disposal Ordinance |
7005123 |
9 Mar 2007 |
N/A |
Valid |
Table 3.5 Summary of submission status under FEP-04/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management
Organization of Main Construction Companies |
11 June 2010 |
Conditions 2.7 and
2.8 |
Submission of works schedule and location
plan |
11 June 2010
and 5 August 2010 |
Condition 2.9 |
Noise Management
Plan |
19 October 2010 |
Condition 2.10 |
Landscape Plan |
26 November 2010 |
Contract
no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
3.1.5.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under
FEP-02/364/2009 for
contract no. HK/2009/01 are shown in Table 3.6 and Table 3.7
Table 3.6 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
Further Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
Billing Account
under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.7 Summary of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of Submission |
NIL |
NIL |
NIL |
Contract
no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
3.1.6.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under
FEP-01/364/2009 for
contract no. HK/2009/02 are shown in Table 3.8 and Table 3.9.
Table 3.8 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31 Mar 2015 |
Valid |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
28 July 2010 |
31 Jul 2015 |
Valid |
|
Billing Account
under Waste Disposal Ordinance |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration as
Chemical Waste Producer |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Table 3.9 Summary of submission status under FEP-01/364/2009
EP Condition |
Submission |
Date of Submission |
NIL |
NIL |
NIL |
Contract no. HY/2009/18 - Central - Wan Chai Bypass
(CWB) – Central Interchange under FEP-05/364/2009/A
3.1.7.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.10 and Table 3.11.
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/18
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further
Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
N/A |
Valid |
Notification of
Works Under APCO |
322293 |
07 Oct 2010 |
N/A |
Valid |
Discharge Licence |
WT00008229-2011 |
13 Jan 2011 |
31 Jan 2016 |
Valid |
Billing Account
under Waste Disposal Ordinance |
7011587 |
11-Oct-10 |
N/A |
Valid |
Registration as a
Waste Producer |
WPN:
8335-121-L1048-04 |
17 Dec 2010 |
N/A |
Valid |
Table 3.11 Summary of submission status under
FEP-05/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management
Plan |
01-Mar-11 |
Condition 2.10 |
Landscape Plan |
26 Jan 2011 |
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
3.1.8.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under
FEP-06/364/2009/A for
contract no. HY/2009/15 are shown in Table 3.12 and Table 3.13
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental
Permit |
22 Nov 2010 |
N/A |
Valid |
|
22 Nov 2010 |
N/A |
Valid |
||
Notification of Works
Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Billing Account under
Waste Disposal Ordinance |
7011553 |
30 Sep 2010 |
N/A |
Valid |
Table 3.13 Summary of submission status under
FEP-06/364/2009/A
EP Condition |
Submission |
Date of Submission |
NIL |
NIL |
NIL |
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
3.1.9.
The current status on licences and/or permits on environmental
protection pertinent and submission under FEP-07/364/2009/A for contract no. HY/2009/19 are shown in Table 3.14 and Table
3.15.
Table 3.14 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/19
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further
Environmental Permit |
25 Feb 2011 |
N/A |
Valid |
|
Notification
of Works Under APCO |
326160 |
24 Jan 2011 |
N/A |
Valid |
Registration
as a Waste Producer |
7012306 |
10 Feb 2011 |
N/A |
Valid |
Registration
as Chemical Waste Producer |
5213-151-C3654-01 |
24 Mar 2011 |
N/A |
Valid |
Table 3.15 Summary of submission status under FEP-07/364/2009/A
EP Condition |
Submission |
Date of Submission |
NIL |
NIL |
NIL |
Noise Monitoring Stations
4.1.1. The noise monitoring stations for the Project
are listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for
the monitoring works.
Table
4.1 Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire
Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
Real
time Noise Monitoring Stations
4.1.2.
The
noise monitoring stations for the Project are listed and shown in Table
4.2 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels for
the monitoring works.
Table 4.2 Real Time Noise
Monitoring Stations
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
Noise Monitoring
Parameters, Frequency and Duration
4.1.3. The construction noise level
shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq).
Leq (30 minutes) shall be used as the monitoring parameter for the
time period
between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq
(5 minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
4.1.4. Noise monitoring shall be carried out at all the
designated monitoring stations. The monitoring frequency shall depend on the
scale of the construction activities. The following is an initial guide on the
regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
4.1.5. Real time noise shall be carried out at the designated
monitoring stations. The following is an initial guide on the regular
monitoring frequency for each station on a 24 hours daily basis when noise
generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
·
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
·
One
set of measurements between 2300 and 0700 hours on next day on everyday.
4.1.6. If construction works are extended to include works
during the hours of 1900 – 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring Equipment
4.1.7. As referred to in the Technical Memorandum ™ issued
under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
4.1.8. Noise measurements shall not be made in fog, rain,
wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s.
The wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m/s.
4.1.9. The sound level meter shall be checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency before deployment to the site and during each site visit.
Measurements may be accepted as valid only if the calibration level from before
and after the noise measurement agree to within 1.0 dB.
Air Quality Monitoring
Stations
4.2.1. The air monitoring stations for the Project are
listed and shown in Table 4.3 and Figure 4.1.. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.3 Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Community
Liaison Centre |
North Point |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office * |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
|
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (western End of Podium) |
Central |
* Remarks:
As per the ENPC meeting in February 2011, the monitoring stations CMA3a - Future
CWB site office at Wanchai Waterfront Promenade was renamed as remark.
Air Monitoring Parameters,
Frequency and Duration
4.2.2. One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
4.2.3. All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail.
4.2.4. For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and
Monitoring Equipment
4.2.5. High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
·
0.6
- 1.7 m3 per minute adjustable flow range;
·
Equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
·
Installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
Capable
of providing a minimum exposed area of 406 cm2;
·
Flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
Equipped
with a shelter to protect the filter and sampler;
·
Incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
Equipped
with a flow recorder for continuous monitoring;
·
Provided
with a peaked roof inlet;
·
Incorporated
with a manometer;
·
Able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
Easily
changeable filter; and
·
Capable
of operating continuously for a 24-hour period.
4.2.6. Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
Laboratory Measurement /
Analysis
4.2.7. A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8. Filter paper of size 8" x 10" shall be
labeled before sampling. It shall be a clean filter paper with no pinholes, and
shall be conditioned in a humidity-controlled chamber for over 24-hours and be
pre-weighed before use for the sampling.
4.2.9. After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall
then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
4.2.10. All the collected samples shall be kept in a good
condition for 6 months before disposal.
4.2.11. Current calibration certificates of equipments are
presented in Appendix
4.2.
5.0.1. The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various
contracts, latest status of work commencement and monitoring stations is shown in
Figure
2.1 and Figure 4.1. The monitoring results
are presented in according to the Individual Contract(s).
5.0.2. In the reporting month, the concurrent contracts are
as follows:
Contract
no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
Contract
no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009
5.0.3. The environment monitoring schedules for reporting
month and coming month are presented in Appendix 5.1.
Contract no. HY/2009/17 –Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
5.1.1.
The
proposed division of noise monitoring stations for Contract no. HY/2009/17 are
summarized in Table 5.1 below:
Table
5.1 Noise Monitoring Stations for Contract no. HY/2009/17
Station |
Description |
M4b |
Victoria Centre |
5.1.2.
No
action and limit level exceedance was recorded during day time and restricted
hour period in the reporting month. Noise monitoring results measured in this
reporting period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix 5.2.
Contract no.
04/HY/2006 – Reconstruction of
Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A and Contract no. HY/2009/18 - Central - Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
5.1.3.
The
proposed division of noise monitoring stations for Contract no. HY/2009/18 and 04/HY/2006
are summarized in Table 5.2 below:
Table
5.2 Noise Monitoring Stations for Contract no. HY/2009/18 and 04/HY/2006
Station |
Description |
M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
5.1.4.
The
commencement of major construction works for Contract no. HY/2009/18 under
FEP-05/364/2009A is pending. Only preparation
works was commenced in the reporting month. In addition, major
construction works for Contractor no. 04/HY/2006 was completed. As such, no
noise monitoring at M7e and M7w were conducted in this reporting month.
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre - Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
5.1.5.
The
commencement of construction works for Contract no. HK/2009/01 and HK/2009/02
under FEP-02/364/2009 and FEP-01/364/2009 respectively are pending. The
proposed division of noise monitoring stations are summarized in Table
5.3 below.
Table
5.3 Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
Contract no.
HY/2009/15 - Central-Wanchai Bypass – Tunnel (
5.1.6.
The commencement of
construction works for Contract no. HY/2009/15 under FEP-06/364/2009/A is
pending. The proposed division of noise monitoring stations are summarized in
Table 5.4 below.
Table
5.4 Noise Monitoring Stations
for Contract no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/A
5.1.7.
Noise monitoring for
the tunnel works under contract no. HY/2009/19 was commenced on 24 March 2011. The
proposed division of noise monitoring stations are summarized in
Table 5.5 below.
Table
5.5 Noise Monitoring Stations
for Contract no. HY/2009/19
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
5.1.8.
No
exceedance was recorded in the reporting month. Noise monitoring results
measured in this reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/17 –Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009 and Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
Table
5.6 Real Time Noise
Monitoring Stations for Contract no. HY/2009/17
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
5.2.2.
No
exceedance was recorded in the reporting month. Real time noise monitoring
results measured in this reporting period are reviewed and summarized. Details
of real time noise monitoring results and graphical presentation can be
referred to Appendix 5.4 .
5.2.3.
The
proposed division of noise monitoring stations are summarized in Table 5.7
below. Real time noise monitoring for major construction works under contract
no. HY/2009/19 was commenced on 24 March 2011.
Table
5.7 Real Time Noise
Monitoring Stations for Contract no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
RTN2 |
North Point |
|
5.2.4. No exceedance was recorded in the reporting month.
Real time noise monitoring results measured in this reporting period are
reviewed and summarized. Details of real time noise monitoring results and
graphical presentation can be referred to Appendix
5.4 .
Contract no. HY/2009/17 –Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
5.3.1.
The
proposed division of air monitoring stations are summarized in Table
5.8 below. Air monitoring for the piling works under contract no.
HY/2009/17 was commenced on 8 October 2010.
Table
5.8 Air
Monitoring Station for Contract no. HY/2009/17
Station |
Description |
CMA2a |
|
5.3.2.
No
exceedance was recorded in the reporting month. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no.
04/HY/2006 – Reconstruction of
Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A and Contract no. HY/2009/18 - Central - Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
5.3.3.
The
proposed division of air monitoring stations are summarized in Table
5.9 below.
Table
5.9 Air
Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of Podium) |
MA1w |
International Finance Centre (Western End of Podium) |
5.3.4.
The
commencement of major construction works for Contract no. HY/2009/18 under
FEP-05/364/2009A is pending. Only preparation
works was commenced in the reporting month.
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at
5.3.5.
Air quality
monitoring
will be commenced depending on the commencement of work for Contract no.
HK/2009/01 under FEP-02/364/2009. The proposed division of air monitoring stations
are summarized in Table 5.10 below.
Table
5.10 Air
Monitoring Station for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to |
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
5.3.6.
Air quality
monitoring
will be commenced depending on the commencement of work for Contract no.
HK/2009/02 under FEP-01/364/2009. The proposed division of air monitoring stations
are summarized in Table 5.11 below.
Table
5.11 Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Contract no.
HY/2009/15 - Central-Wanchai Bypass – Tunnel (
5.3.7.
Air
quality
monitoring will be commenced depending on the commencement of
work for Contract no. HY/2009/15 under FEP-06/364/2009/A. The proposed division of air
monitoring stations are summarized in Table 5.12
below.
Table
5.12 Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under
FEP-07/364/2009/A
Table
5.13 Air Monitoring
Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil St Community Liaison Centre |
CMA2a |
|
Contract no. HY/2009/17
–Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling
works under FEP-03/364/2009
5.4.1. No Inert C&D waste was recycled in the
reporting month. Details of the waste flow table are summarized in Table
5.14
Table 5.14 Details of Waste Disposal for Contract no.
HY/2009/17
Waste Type |
Quantity this month, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
N/A |
||
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
N/A |
N/A |
N/A |
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street
and Man Kwong Street under FEP-04/364/2009/A
5.4.2. No inert C&D waste was disposed of in this reporting
month. Details of the waste flow table are summarized in Table 5.15.
Table 5.15 Details of Waste Disposal for Contract no. 04/HY/2006
Inert C&D materials disposed |
NIL |
1288.5 |
Chai Wan and T.K.O. 137 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract nos. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at
5.4.3. No inert and non-inert C&D waste was disposed
of in this reporting month. Details of the waste flow table are summarized in Table
5.16.
Table
5.16 Details of Waste Disposal for Contract no. HK/2009/01
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
5.4.4. No inert and no-inert C&D waste was disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.17.
Table
5.17 Details of Waste Disposal for Contract no.
HK/2009/02
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract no. HY/2009/18 - Central - Wan Chai Bypass
(CWB) – Central Interchange under FEP-05/364/2009/A
5.4.5. Inert C&D and Non-inert C&D waste was
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.18.
Table 5.18 Details of Waste Disposal for Contract no. HY/2009/18
Inert C&D materials disposed |
104.7 |
104.7 |
T.K.O. 137 |
Inert C&D materials recycled |
0 |
0 |
N/A |
Non-inert C&D materials disposed |
8.2 |
49.2 |
SENT Landfill |
Non-inert C&D materials recycled |
0 |
0 |
N/A |
Chemical waste disposed |
0 |
0 |
N/A |
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
5.4.6. No inert and no-inert C&D waste was disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.19.
Table 5.19 Details of Waste Disposal for Contract no. HY/2009/15
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel
(North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
5.4.7. No inert and no-inert C&D waste was disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.20.
Table 5.20 Details of Waste Disposal for Contract no. HY/2009/19
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
6.0.1. The Event Action Plan for construction noise, air
qualities are presented in Appendix 6.1.
Contract no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
6.1.1.
No exceednace was recorded in the reporting month.
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street
under FEP-04/364/2009/A
6.1.2.
No noise monitoring was undertaken in the reporting
month.
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
6.1.3.
No noise monitoring was undertaken in the reporting
month.
Contract nos. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at
6.1.4.
No noise monitoring was undertaken in the reporting
month.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
6.1.5.
No noise monitoring was undertaken in the reporting
month.
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
6.1.1
No exceednace was recorded in the reporting month.
Contract
no. HY/2009/17 – Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
6.1.6.
No exceednace was recorded in the reporting month.
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
6.2.1
No exceednace was recorded in the reporting month.
Contract no. HY/2009/17 – Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
6.3.1.
No exceedance was recorded in the reporting month.
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street
under FEP-04/364/2009/A
6.3.2.
No air quality monitoring was undertaken in the
reporting month.
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
6.3.3.
No air quality monitoring was undertaken in the
reporting month.
Contract nos. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at
6.3.4. No air quality monitoring
was undertaken in the reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
6.3.5. No air quality monitoring
was undertaken in the reporting month.
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
6.3.1
No exceednace was recorded in the reporting month.
6.3.1. There was no non-compliance from the site audits in
the reporting period. The observations and recommendations made in each
individual site audit session were presented in Section 8.
6.3.2. No project-related non-compliance from monitoring
was recorded in the reporting month.
6.4.1. There was no particular action taken since no project-related
non-compliance was recorded from the site audits and environmental monitoring
in the reporting period.
7.0.1. According to Condition 3.4 of the EP-364/2009/A,
this section addresses the relevant cumulative construction impact due to the
concurrent activities of the current projects including the Central Reclamation
Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass
(CWB) and Island Eastern Corridor Link projects (IECL).
7.0.2. From the Monthly EM&A report (March 2011) of
Central Reclamation Phase III the key works in March 2011 are as follows:
·
Type A filling in FRAW and FRAE above +2.5mPD
·
General filling works above +2.5mPD in IRAE
·
Surcharging in FRAW and FRAE
·
Construction of cantilever slab at caisson
·
Base slab, wall and roof construction at Culvert F
·
Construction of storm and foul drainage and gullies
in hinterlands for Road P2, Road D7, and Road D9
·
Construction of GPO boundary wall
·
Construction of PLA boundary wall
·
Construction of Promenade enhancement works
·
Construction of buildings at PLA berth
·
Road P2 Underpass ramp structures
·
Precasting for retaining wall (offsite)
·
Installation of cooling mains discharge pipes in
FRAE and FRAW
·
Bulk excavation to formation level at CWB works
·
Construction of CWB structure
·
Disposal of material off-site to Government fill
banks
·
Strengthening of
7.0.3. According to the construction programme of Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects, the major construction activity under Wan Chai Development Phase II was
the filling works at North Point Reclamation Stage 1(NPR1), dredging works at Wan
Chai Reclamation Stage 1(WCR1), Advanced
piling works at FEHD Whitfield Depot and cross-harbour water mains in the reporting
month. The major environmental impact was water quality impact at North Point
and Wan Chai. Land-based construction activity was only advance piling works at
FEHD Whitfield Depot in the reporting month.
7.0.4. The major environmental impacts generated from the
Central Reclamation Phase III were located along the coastline of Central and
Admiralty while advanced
piling works at FEHD Whitfield Depot were undertaken in the reporting month. No significant
air, noise impact were anticipated in the reporting month. Besides, no
environmental monitoring exceedance was recorded from the Project in the
reporting month. Thus, it is evaluated
that the cumulative construction impact from the concurrent projects including
Wan Chai Development Phase II and Central Reclamation Phase III was
insignificant.
8.0.1. During this reporting month, weekly environmental
site audit was conducted for Contracts no. HY/2009/17. No non-conformance was
identified during the site audits.
8.0.2. Four site inspections for Contract no. HY/2009/17 were
carried out during this reporting period. The results of these inspections and
outcomes are summarized in Table 8.1.
Table
8.1 Summary of Environmental Inspections for Contract no. HY/2009/17
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
110316_01 |
16-Mar-11 |
Regular
water spraying on unpaved road shall be provided for dust supression. |
Sprayed
water on the haul road. |
Completion
as observed on 22-Feb-11 |
110316_02 |
16-Mar-11 |
Floating
debris on the stagnant water shall be cleared up. |
Clearance
of the floating debris in the ponding water. |
Completion
as observed on 22-Feb-11 |
110322_01 |
22-Mar-11 |
Silty
water was found around the gully at site
entrance. Contractor was reminded to clear it up. |
Clear the mud around the gully |
Completion as observation on 29- Mar-11 |
8.0.3. No site inspections for Contract no. HY/2009/19 was
carried out during this reporting period.
8.0.4. Major construction works were completed and Engineer’s confirmation for completion of
work is under processing in
this reporting month. No site inspection for Contract no. 04/HY/2006 was
carried out during this reporting period.
9.0.1. No complaint, notification
of summons and prosecution was received in the reporting month. The details of
cumulative complaint log and updated
summary of complaints are presented in Appendix
9.1.
9.0.2. Cumulative statistic on complaints and successful
prosecutions are summarized in Table 9.1 and Table 9.2 respectively.
Table 9.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
March 2011 |
0 |
Sep 10 to
Feb 11 |
0 |
Table 9.2 Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
10.0.2. The scheduled construction activities and the
recommended mitigation measures for the coming month are listed in Table
10.1. The construction programmes of individual contracts are provided
in Appendix 10.1.
Table 10.1 Summary of Key Construction Activities of
Individual Contract(s) to be commenced in Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation Measures |
HY/2009/17 |
·
Drilling,
installation steel H-Pile & grouting |
·
Noise barrier
shall be implemented; ·
Watering any dust
generating activities; and Improvement of wheel washing facilities Improvement and increasing the number of sedimentation tanks. · |
HY2009/19 |
·
Installation of
working platform and marine pre-drilling |
·
Noise level shall
be controlled by reducing drilling rate. |
10.0.3.
Major
construction works for Contract no. 04/HY/2006 were completed and Engineer’s confirmation for completion of work is under processing in this
reporting month.